Just to get this thread back on track (there is every other thread on this f**king forum that can be derailed guys).
A concrete pour was happening at the southern end of the western grandstand today, meaning pretty much that the aerial photo I posted above now has the western grandstand completed at ground level all the way to the south end. Much of it is already up to first floor level. Don't forget that the western grandstand is similar to a 5 story building. So, lot's to do there yet.
Stuart Ayres apparently also claimed today on the radio that the govt is hoping for a May 2019 completion.
From what I saw today, it will be an ask to complete the stadium in 16 months. They may very well be able to accomplish this but up till this stage, they've had a remarkable run of fine weather. History tells us that after a drought comes flooding rains. There will no doubt be weather delays during this period.
There just seems to be so much to do in 16 months.
In saying that, just 12 months ago, they were only just beginning to demolish the old shithole, so I suppose anything is possible.
Structural steel for the roof is onsite and the 400 tonne crane has been erected so I expect the roofing steel to be beginning to be installed soon.